Starke County
1793 ACRES USEABLE FARMLAND | 200 MW
DEVELOPMENT TIMELINE
Site Control: 5/2020-12/2022
Interconnection: 6/2021-4/2023
Permitting: 9/2022-10/2023
System Design: 5/2022-4/2023
Procurement: 9/2022-12/2023
Construction Begins: 12/2023-11/2024