Starke County

1793 ACRES USEABLE FARMLAND | 200 MW

DEVELOPMENT TIMELINE

  • Site Control: 5/2020-12/2022

  • Interconnection: 6/2021-4/2023

  • Permitting: 9/2022-10/2023

  • System Design: 5/2022-4/2023

  • Procurement: 9/2022-12/2023

  • Construction Begins: 12/2023-11/2024