Adams County
1,984 ACRES OF TOTAL FARMLAND | 346 MW
DEVELOPMENT TIMELINE
Site Control: 1/2020-2/2022
Interconnection: 5/2021-5/2022
Permitting: 4/2022-12/2022
System Design: 1/2022-12/2022
Procurement: 5/2022-1/2023
Construction Begins: 10/2022-5/2023